Dam Updates

Home Page

Calendar

Special Events /
 Announcements

DAM UPDATES

Newsletter

Minutes & Reports

Board Members

General Discussion

Rules & Regulations

Photo Galleries

Useful Links

 

 

DAM REPAIR IS UNDERWAY

September 2, 2008

     The Board received bids on dam repair and is looking into financing. Also reviewed bids for the silt removal and keeping soil in GA. Once we get references on the bidders we can award the jobs. Once we know the amount to finance, we can talk about the Specail Assessment. Thanks for your patience.

 

Lake Update and The Question of Dredging

From Debbie Lambert Baugher, Chairman

 

The Board has received several inquiries concerning having areas of the lake dredged. We have spoken with three contractors who have done this type of work. I walked the perimeter of the lake with them along with members of the Lake Committee that was formed last year. We have asked these contractors to submit sealed bids for the work by July 11, 2008 which will allow us to have that information at the Annual Meeting.

 

There are many reasons to consider this work.

  1. While the lake is drained, all areas are accessible. It would be less expensive to do it now rather than when the lake is full.
  2. Through the last 30+ years that the lake has been a part of Greene Acres, to my knowledge, no such work has ever been performed. Years of normal run-off accompanied by increased building has sent several feet of sediment into the lake.
  3. Most of this sediment has settled at the North end of lake where the main stream feeds in, but nearly the entire shoreline has been affected.
  4.  From information we have received, the normal guideline used to determine a grade for the shoreline is that at 6ft from the shore, the water should be 3 ft deep. Keeping in mind that this is just an estimate, there are several areas that need attention.
  5. One of the reasons we had an issue with so much grass along the shoreline is because areas of the lake had filled in. We have been advised that grass will die off if the water is at a depth of at least 3 to 4 feet.
  6. Lastly, the 5 streams that feed Greene Acres Lake have also become filled in through the years and at the very least, these need to be deepened and restored to their original state.

 

There are also other factors to take into consideration. With dredging, some of the sediment can be pushed into the deeper parts of the lake, but the majority of it would have to be removed. This could amount to MANY dump truck loads that would need to be disposed of. We will be trying to obtain soil samples to determine the quality of this dirt. Although, some of it may be considered topsoil, the contractors tell us that it will most likely be considered fill dirt. There had been discussions that possibly this dirt could be sold, but if what we have been told is true, it will be considered unscreened fill dirt which has no value. Further, we must have the dirt hauled and deposited somewhere.

 

The fill dirt would first be made available to any homeowners within the subdivision.. However, there may are County guidelines that govern this. For any owner with lakefront property, silt fences would have to be installed prior to the dirt being deposited. Since this may basically be dirt with no nutrients, in order for it to be usable it would require additives. The estimate is that it could be 2 to 3 years before anything may grow in it. If the dredging takes place, there will be more information provided by the Lake Committee to homeowners who may want the fill dirt.

 

If all of the dirt cannot be disposed of within Greene Acres, the contractors will have to haul it out which could be quite costly depending on the distance they have to travel. Some places charge to take fill dirt. We are looking at options for that now and have two outside sources who are willing to take some of the dirt.


The Lake Committee is investigating any State or Local permits that may be required if we go forward with

this project.

 

Dredging would be a benefit to all of us as Property Owners as it extends the life and health of the lake.  It contributes greatly to our property value and gives much enjoyment to all of us. It has provided a habitat for local wildlife and water fowl. As we all agree, it is one of the most beautiful lakes in Greene County and we have a responsibility to maintain it for our heirs.

 

First and foremost, we must wait until we have estimates on the dam repair. We are still waiting for the Engineer to finalize the plans. The long wait has been frustrating for all of us especially as we see the summer slipping by and no work has begun. Please know that each of us on the Board shares this frustration.

 

Because we have no estimates on the dam repair or dredging the lake, we have no idea what dollar figure to consider. When the beach flooded in the 90’s a Special Assessment was assigned to each Property Owner for a specific number of years to make payments on a loan from the Small Business Administration. Due to the diligence and management of our funds, our Treasurer was able to pay that loan off early.

 

Please know that the Board fully understands that this is YOUR money we are working with. You elected each of us to represent your best interests in handling these funds and in making decisions that affect each of us. We don’t take this responsibility lightly. The Board Members are volunteers. We all work full-time jobs just like you and we try to balance that along with raising our families. We are dedicated to Greene Acres and work together with you to make it a great place to live. Any decisions made will be thoroughly investigated and all options explored before implementation.

 

As always, any of us on the Board are available to answer questions. We certainly don’t claim to be experts on dam and lake issues, but we aren’t afraid to ask questions, no matter how simple they may seem to some. We also welcome your constructive input.

 

.           Thanks for your continued patience.

 

May 19, 2008

LATEST UPDATE TO GREENE ACRES LAKE AND DAM ISSUE

 

            Here is what we’ve learned:

            With all of the rain, work to determine the cause of the dam breach was delayed, but has now been completed. Chip Morris was contracted by the Board to construct the temporary dam to hold the water back from the drain pipe. Once that was completed, Roto-Rooter was able to remove debris from the pipe and insert a camera. A video was made and given to our Civil Engineer, Kurt Kloeckner. After evaluating what he saw, he has determined that sections of the bottom of the pipe have degraded, causing the leaks. Of all of the possibilities, this is the one we were hoping to find. Repairs for this will be considerably less than what was projected when the problem was discovered Easter morning.

             The next step:

 The Board has the plans from the Engineer for the repairs to the dam. As soon as we have word from the Regional Engineer that those plans meet the State Board’s approval, we will advertise the job. The bidding process will be posted on the website as well as the local paper. Once we have the okay to proceed and the bidding process is complete, we will select a Contractor to begin the work.

 At this point, we have no way to estimate the time it will take until the job is complete. But, it is clear that the lake will not be available for use this season even when the dam is repaired and the lake begins to fill. 

Our thanks to Carol and Ken Weiss for the research they have done on reclaiming our lake. They had volunteered last year to head up a committee to protect the lake. Little did we know then what we would be facing now, so their efforts are greatly appreciated.  Ken will be on the Agenda for our July 19th Annual Meeting to share what he has learned and offer suggestions on restocking. In the meantime, there are things that can be done to better prepare a habitat for the fish and maintain an ecological balance for the lake. We look forward to what he has to share

            I will post another update after the bids are in and we have information on the cost of the repairs. I know how frustrating this is and there have been comments on this website suggesting that the Board has “stonewalled” the information, or that folks know more from gossip than what they hear from the Board or that there is no “management” of the Board.  The Board does not deal in “gossip” we deal in facts. We have reported to you as we have those facts and will not speculate as to what may happen or what the cost may be. You are certainly free to believe what you choose. Remember that each member of the Board performs their duties on a volunteer basis…..that means no monetary compensation. We serve because this is our home and we care about maintaining it. There are committees open to anyone interested in working with us. As is the case every year, there are 3 Board positions that will be open. We already have some folks that have submitted their names for nomination and we welcome any of you to do so. Contact Jim Mathis, Nominating Chairman.

 Thanks,

Debbie Lambert

Chairman

 

 

April 27, 2008

 

GREENE ACRES PROPERTY OWNERS ASSOCIATION

UPDATE TO DAM ISSUE

 

TO RE-CAP:

 

On March 23, 2008, a leak in the dam was discovered. After consultations with the Regional Dam Inspector and Kloeckner Engineering, the decision was made that the lake needed to be drained in order to properly assess the situation.

The Emergency Action Plan was put into to place and residents in below the dam were notified by the Greene County Sheriff’s Department.

Since that time, the water level reached a point where fish could be netted. Thousands were recovered and were relocated to ponds and lakes throughout Greene County.

 

WHERE WE ARE:

 

The assumption is that the leak was probably caused by the age of the dam. The Engineers did not feel that there were any contributing factors other than that.

Within the last two weeks, the emergency flow pipe was exposed as the water level decreased. Work was done to shorten the pipe so that the remaining water could drain.

 

THE NEXT STEP:

 

The next step will be to have a small, temporary dam constructed to protect this exposed drain. This will allow the lake to fill in behind the temporary dam and create a dry access to the exposed pipe. When this is achieved, a cable with a camera attached will be inserted. A video will be made of the inside of the pipe which the Engineers will use to assess where the pipe is compromised. Once this is done, the Engineer will make the recommendations as to how to repair the pipe. He will provide the specifications for that process which the Board will use to put the work out for bids.

The heavy rain this week-end may push this process back a few days, but it will be done as soon as feasible.

At this point, there is still no definite estimate on the cost to the Association. But the expectation is that if the pipe can be repaired without having to excavate the dam, the cost will not be as high as originally suggested.

 

LOOKING FORWARD:

 

Once we have some answers from the Engineers, we will know how to proceed. Until then, there are many options that need to be considered. The Board’s desire is to move slowly and take this time to investigate what can be done to make the dam as safe as possible so that future homeowners will not have to deal with this issue again. Also, to consider what needs to be done to insure that as the lake fills and is re-populated, we have done everything we can to insure the survival of the fish and wildlife. We want to make sure that the lake again becomes a place for the owners to enjoy.  There is also work that should be done to the tributaries that feed the lake.

 

Your comments are appreciated and we welcome your involvement in offering suggestions.

 

Thanks for your patience,

Debbie Lambert

Chairman, GAPOA

 

 

                                                                                                                                                                                                                                                       

GREENE ACRES PROPERTY OWNERS ASSOCIATION

EMERGENCY ACTION PLAN

SERIES OF EVENTS ON MARCH 23, 2008

CHAIRMAN’S REPORT

SUNDAY, MARCH 23, 2008

9:15AM Property Manager, Tommy Darnell arrived at home of Chairman, Debbie Lambert to report that he had observed water bubbling up through the ground near the Emergency Valve. He enlisted the assistance of Wesley Baugher to make an assessment on the course of action to be taken.

9:45 AM Knowing that any issue involving the dam could result in an emergency, and following the guidelines of the GAPOA Emergency Action Plan, Tommy and Wesley contacted Greene County Sheriff, Scott Hass, who returned with them to the dam. Debbie Lambert then contacted all members of the Board of Trustees who could be reached by telephone.

10:00 AM Sheriff Haas’ concurred that indeed the possibility of an emergency existed, and again, following the GAPOA EAP Guidelines, immediately dispatched deputies to notify homeowners identified by that plan as being in harm’s way should an emergency arise.

Attempts were made to contact Kloeckner Engineering, the company contracted to perform dam inspections and various State and Local Agencies including the Department of Conservation and Recreation which is responsible for dam safety.

1:00 PM The Albemarle Sheriff’s Department assisted Sheriff Hass by reaching Kurt Kloeckner of Kloeckner Engineering who arrived around 1:00 PM. He examined the area around the Emergency Valve and the slope of the dam and believed that it was possible the water was draining from a leak in the pipe leading to the Emergency Valve. He then contacted Jack Campbell, owner of Faulkner Construction whom he knew to be familiar with dam construction. He asked that the Emergency Valve be opened partway to relieve pressure on the pipe. Steve Catalana, Chairman of the Greene County Board of Supervisors was also present.

2:30 PM Mr. Campbell arrived and asked that the Board contact any local contractor who was familiar with dam construction and would be available to immediately excavate the area surrounding the pipe in order to assess the situation.

4:00 PM Chip Morris of Fox Hill Farms arrived with the equipment needed to uncover the pipe. Initially, the thought was that a leak might be discovered in the area of the first few feet of pipe and then plans could be made to repair. A side-ditch was created to divert the flow of water into the creek. As the excavation continued, it became apparent that the water did not seem to be originating from the pipe, but rather from the area surrounding the pipe. To further support that theory, Mr. Morris, under the direction of Mr. Campbell continued to excavate the area surrounding the pipe until a distance of about twenty-five feet was reached. Mr. Kloeckner and Mr. Campbell then agreed that it would not be in the interest of safety to continue this process. The Board was instructed to cordon off the area to deter onlookers and to monitor the flow of water constantly for any change in water quality or water pressure.

At this point, steps were taken to follow through with the instructions given by the Engineer. Various Property Owners assisted in this process.

 

MONDAY, MARCH 24, 2008

12:00PM Robert VanLier, Dam Safety Regional Engineer arrived to inspect the dam. He then determined that the only way to truly assess the seriousness of the situation was to lower the water level of the lake to expose the area of the dam that has been compromised. This could take up to a month to complete.

Until that time, any discussions are purely speculative. No decisions can be made until the situation has been evaluated by the Engineers.

TUESDAY THRU FRIDAY, MARCH 25 – 28, 2008

Draining of lake is being monitored virtually 24 hours a day.

Dam Safety Engineer visits dam frequently to insure that the flow of water from lake was not too fast as to cause further damage to dam.

Various County officials stop by frequently

SATURDAY, MARCH 29, 2008

An Informational Meeting was held at County Administrative Building was open to all Homeowners... Mr. VanLier, the Regional Dam Safety Engineer, explained that until the water level reaches the depth that exposes the pipe in the lake, we cannot know what the solution will be. We are retaining the services of Kurt Kloeckner of Kloeckner Engineering to guide us through this process. When he can assess the situation, he will make recommendations. Until then, we are using this time to plan for the recovery of the lake once the dam is repaired.

We have been in contact with Biologists from the Department of Game and Inland Fisheries concerning the fish that inhabit the lake. Corey Quinn, Chairman of the Environmental Committee will post the information he gathered on the website in few days.

-Debbie Lambert

Chairman, Board of Trustees

______________________________________________________________________________________________

 

THE DAM IS LEAKING

March 24, 2008

 

The Board is taking every action to keep the community safe and to protect the integrity of the dam. 

 

The Board has sought the help of engineers including a Dam Safety Regional Engineer.

 

 

The lake is in the process of being drained and further repair options are being considered. 

 

More information is forthcoming.

 

ACTION:   Remove all items from the lake.  Stay out of the beach and dam area.

 

Continue to check the website for updates or contact a Board Member.

www.gapoa.org

 


Debbie Lambert, Chairman

434-990-0226

Dana Friend, Vice-Chairman  -  Newsletter Editor

434-985-6844

Mark Beifuss, Secretary

434-985-1867

Lisa Goodwin, Treasurer

609-645-9471

John Ferritto, Legal & Insurance

434-985-4451

Cory J. Quinn, Environmental Control

434-990-5720

Adam Stoffel, Roads & Facility

434-566-8376

Tere Vann, Safety & Services

540-903-6751

Jim Mathis, Membership & Nominating

434-985-3166

Tommy Darnell, Property Manager

434-249-3850

 

Copyright © 2008 Greene Acres Property Owners Association.
For problems or questions regarding this web contact Webmaster.
Last updated: 12/31/08.

 

Hit Counter